First tranche of proposed changes to Victoria's Security of Payment legislation

12 minute read  11.09.2025 Chris Hey, Jeanette Barbaro, Nikki Miller

The Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Bill 2025 (Bill) was read for a second time in Victoria's Legislative Assembly on 11 September 2025.


Key takeouts


  • The Bill proposes substantial changes to Victoria's SOP Act, which has remained unchanged since 2006. The most substantial change proposed is the abandonment of Victoria's unique "excluded amounts" regime.

  • However, there are other significant changes proposed including the power to declare notice-based time bar provisions "unfair" and the treatment of performance security under a construction contract.

  • Other changes seek to better align Victoria's SOP Act with other jurisdictions, in particular NSW and Western Australia.    

Background to the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Bill 2025 (Bill)

 

In 2023, the Victorian government announced a parliamentary inquiry into the protection afforded to subcontractors for non-payment including under the Building and Construction Industry Security of Payment Act 2002 (Vic) (SOP Act). The inquiry was conducted by the Environment and Planning Standing Committee.  Following the inquiry, the Report of the Environment and Planning Committee of the Victorian Legislative Assembly was issued on 28 November 2023 (Report) and made 28 recommendations, including major changes to the SOP Act. 

 In October 2024, the Victorian Government provided its response to the Report.  The Victorian Government supported all 28 recommendations, 16 in full and 12 in principle or in part.

On 11 September 2025, the Bill was read for the second time in the Legislative Assembly.  The Bill proposes to implement many of the recommendations from the Report, including by: 

  • repealing the "excluded amounts" regime;
  • repealing the concept of "reference dates";
  • precluding the inclusion of "new reasons" in a payment schedule;
  • extending the time for submission of payment claims;
  • introducing a new power to declare notice-based time bar provisions "unfair" and of no effect;
  • introducing a maximum time period for a respondent to make payment.

     

    In addition, the Bill proposes to go beyond the recommendations in the Report by:

     

  • entitling a party to make a claim for release of the whole or part of a performance security, and apply to a court or make an adjudication application in relation to the performance security claim; and
  • requiring a party to issue a notice of intention to have recourse to performance security at least 5 business days before having recourse.

 

Key changes to the Security of Payment landscape in Victoria 

Excluded amounts and claimable variations Navigation Show below Hide below

The Victorian SOP Act is well known for being unique in prohibiting the inclusion of certain categories of claims or entitlements, defined to be "excluded amounts", in payment claims or payment schedules. This results in certain contractual claims, such as:

  • most entitlements relating to variations;
  • latent conditions; and
  • time related costs (i.e. delay costs as well as liquidated damages),

from being pursued and recovered under the SOP Act.  Because of the "excluded amounts" regime in the SOP Act, the position as to interim entitlement to payment under the SOP Act often deviates from the position as to entitlement to progress payments under the Contract, and compels parties to pursue (often more costly) final dispute resolution avenues to determine their contractual entitlements.

The Bill proposes to repeal sections 10A and 10B of the SOP Act, thus removing the concepts of "excluded amounts" and "claimable variations".  This change will substantially broaden the type of claims that can be referred to adjudication in Victoria. 

Reference dates Navigation Show below Hide below

The issue of whether there is a valid "reference date", being a date on and from which a claimant has a right to make a progress payment, has been the subject of a large number of judicial review applications under the SOP legislation.

The Bill proposes to remove the "reference date" concept, and instead gives claimants the right to submit one payment claim on and from the last day of a month. 

The Bill further proposes that:

  • a payment claim submitted early is not invalid, but the time within which the person may serve a payment schedule does not commence until the earliest date on which the payment claim could have been submitted; and
  • a claimant's entitlement to serve a payment claim is not affected by the termination, or purported termination or the expiry of a construction contract.

New reasons Navigation Show below Hide below

A unique feature of the Victorian SOP Act is that new reasons for withholding payment may be raised by a respondent in an adjudication response, without those reasons first having been included in a payment schedule. The SOP Act then provides a mechanism for the claimant to have an opportunity to respond to any new reasons raised during the adjudication process.

The Bill proposes introducing a prohibition on respondents including new reasons in their adjudication response that were not previously included in the payment schedule, which would align Victoria's adjudication regime with the other jurisdictions.

Time for submission of payment claims Navigation Show below Hide below

The Bill proposes to extend the time within which a payment claim may be served to six months after practical completion of all construction work carried out under the construction contract or after the supply of all related goods and services supplied under the construction contract. 

Powers to declare notice-based time bar provisions "unfair" and of no effect Navigation Show below Hide below

The Western Australian legislature, as part of its significant rewrite of its security of payment laws in 2021, introduced a novel provision that empowers a decision maker (whether an adjudicator, a court, an arbitrator or expert determiner) to declare a notice-based time bar clause of a construction contract "unfair" in certain circumstances, which would result in that time-bar being of no effect in the particular instance that is the subject of the relevant proceeding in which it is declared "unfair". This provision applies beyond security of payment adjudications and can apply in all dispute resolution forums.

The Bill proposes to introduce a similar concept in Victoria through a new section 13A of the SOPA Act.

A notice-based time bar provision may be declared unfair if compliance with the provision is not reasonably possible or would be unreasonably onerous.  The Bill sets out matters which an adjudicator, court, arbitrator or expert must take into account in determining whether a notice-based time bar provision is unfair, which includes the relative bargaining power of each party entering into the contract. 

Recovery of performance security Navigation Show below Hide below

The Bill proposes to introduce new sections 17A to 17G to the SOP Act, which permit a person who claims to be entitled to the release of the whole or a part of a performance security to serve a claim on the person liable to release the performance security. 

A respondent who receives a performance security claim may serve a performance security schedule on the claimant. 

The bill proposes to give rights to claimants to seek release of a performance security by order of the court or through an adjudication application where a performance security schedule is not provided and the respondent does not release the performance security, or through an adjudication application where a performance security schedule is provided but the amounts scheduled to be released are less than the amount claimed. 

Recourse to performance security Navigation Show below Hide below

The Bill proposes to introduce a new s 17H to the SOP Act, which requires a party who intends to have recourse to the whole or part of a performance security under a construction contract to give a notice of intention to have recourse to the performance security at least 5 business days before doing so.  The notice of intention to have recourse must identify the construction contract and the provisions on which the party relies to have recourse, state the amount of the performance security to which the party intends to have recourse and describe the circumstances that entitle the party to have recourse. 

This change aligns the Victorian position with the recent changes in Western Australia.

Commencement

The Bill proposes to introduce a new s 17H to the SOP Act, which requires a party who intends to have recourse to the whole or part of a performance security under a construction contract to give a notice of intention to have recourse to the performance security at least 5 business days before doing so.  The notice of intention to have recourse must identify the construction contract and the provisions on which the party relies to have recourse, state the amount of the performance security to which the party intends to have recourse and describe the circumstances that entitle the party to have recourse. 

This change aligns the Victorian position with the recent changes in Western Australia.

 

 

Contact

Tags

eyJhbGciOiJIUzI1NiIsInR5cCI6IkpXVCJ9.eyJuYW1laWQiOiIzZDY5Y2ZlNC1hMDMzLTRmZTEtYTk5NC1kN2IwMWNkZjRiNTMiLCJyb2xlIjoiQXBpVXNlciIsIm5iZiI6MTc1NzY0MDk1NSwiZXhwIjoxNzU3NjQyMTU1LCJpYXQiOjE3NTc2NDA5NTUsImlzcyI6Imh0dHBzOi8vd3d3Lm1pbnRlcmVsbGlzb24uY29tL2FydGljbGVzL2ZpcnN0LXRyYW5jaGUtcHJvcG9zZWQtY2hhbmdlcy12aWN0b3JpYS1zZWN1cml0eS1vZi1wYXltZW50LWxlZ2lzbGF0aW9uIiwiYXVkIjoiaHR0cHM6Ly93d3cubWludGVyZWxsaXNvbi5jb20vYXJ0aWNsZXMvZmlyc3QtdHJhbmNoZS1wcm9wb3NlZC1jaGFuZ2VzLXZpY3RvcmlhLXNlY3VyaXR5LW9mLXBheW1lbnQtbGVnaXNsYXRpb24ifQ.xooGbRDnCUXg1odu4bo30oZPX60AXw12Vcb3tAuThA4
https://www.minterellison.com/articles/first-tranche-proposed-changes-victoria-security-of-payment-legislation